KNOWLEDGE / 11 MIN READ /

Commercial Tenant Improvement Permits in Los Angeles: 2026 Data and Guide

01
Run a free property check before you read on. LADBS permits, open violations, zoning, and ADU eligibility - in 60 seconds, on your address.
Open Tools →

CCS Data Report – LADBS permits issued through November 21, 2026

We analyzed every commercial alteration permit the City of Los Angeles issued since 2020 and pulled out the tenant improvements. Here is what the data says:

  • LADBS issued 1,244 commercial tenant improvement permits in 2025, and 1,147 so far in 2026 (through November 21), slightly ahead of the 1,131 issued by the same date in 2025.
  • Every one of them went through plan check. Only 1 of 8,599 TI permits since 2020 was issued as an express permit. In 2025, 38.1% went through Expanded Counter Plan Check, 32.7% through Regular Plan Check and 29.1% through same-day Counter Plan Check.
  • The median declared valuation was $100,000. Half of 2025 TI permits fell between $38,350 and $253,025, and 96 were valued at $1 million or more.
  • Offices lead. Office buildings account for 39% of 2025 TI permits, and ZIP code 90067 (Century City) had more than any other.

A commercial tenant improvement (TI) is the work that turns a leased space into a usable office, store, restaurant or clinic: new walls, ceilings, lighting, electrical, plumbing, HVAC, restrooms and finishes, built inside an existing building. In the City of Los Angeles nearly every TI needs a building permit from the Department of Building and Safety (LADBS). LADBS says plainly that commercial tenant improvements “require plan review for accessibility, fire, and life-safety.”

This guide uses the City’s own permit records to show how many TI permits LADBS issues, which plan check path they take, what they are worth and where they happen, then walks through the codes and steps that decide your schedule and budget. It covers the City of Los Angeles only. Cities such as Santa Monica, Beverly Hills, Culver City, Burbank and Glendale, and unincorporated LA County, run their own building departments.

Planning a build-out? See our commercial tenant improvements service, where CCS Inc. designs, permits and builds TI projects across Los Angeles.

What Counts as a Commercial Tenant Improvement

Landlords and brokers use “TI” for any interior build-out a tenant needs before moving in. Typical TI scope includes:

  • Demolition of the previous tenant’s walls, ceilings and finishes
  • New non-bearing partitions, doors, suspended ceilings and flooring
  • Electrical and lighting changes, which must meet the California Energy Code (Title 24, Part 6)
  • HVAC changes, ductwork and rooftop unit replacements
  • Plumbing for restrooms, break rooms, sinks and, for restaurants, kitchens and grease interceptors
  • Accessibility upgrades along the path of travel: entrance, route, restrooms, drinking fountains and signs
  • Fire sprinkler head relocations and fire alarm changes
  • Storefront and signage work on retail spaces

If the work also changes how the space is used, for example retail to restaurant or office to medical, it becomes a change of use, which brings extra review and a new Certificate of Occupancy (more on that below). Since 2020, 1,731 of LA’s TI permits (20%) mention a change of use in the permit description.

How Many TI Permits Los Angeles Issues Each Year

LADBS issues between about 1,150 and 1,400 commercial tenant improvement permits a year. TIs make up roughly a quarter of all commercial alteration permits.

Year issued TI permits All commercial alteration permits TI share
2020 1,149 4,968 23%
2021 1,200 5,447 22%
2022 1,411 6,128 23%
2023 1,189 5,589 21%
2024 1,259 5,347 24%
2025 1,244 5,000 25%
2026 (through Nov 21) 1,147 4,612 25%

Through November 21, 2026, LADBS had issued 1,147 TI permits, compared with 1,131 by the same date in 2025 and 1,139 in 2024. Demand for build-outs has held steady for three years.

The Three Plan Check Paths for a TI

LADBS has an Express Permit for simple work that needs no plan check, but tenant improvements almost never qualify. Only 1 of 8,599 TI permits since 2020 was issued that way. Instead, a TI goes through one of three plan check paths, and which one you land in is the biggest factor in your permit timeline:

Plan check path What LADBS says it covers Share of 2025 TI permits Median 2025 valuation
Counter Plan Check Small and medium projects reviewed the same day as submittal, in about 45 to 60 minutes. Listed project types include a TI with no change in use, and a TI with a change in use but no change in parking. 29.1% $50,000
Expanded Counter Plan Check Larger projects such as a multi-floor TI with no change in use. Plans are assigned within a few days of submittal. 38.1% $101,940
Regular Plan Check Large, complex projects. Plans are reviewed and returned “within weeks depending on workload.” Paying 50% more of the plan check fee expedites the review. 32.7% $190,000

The pattern in the data is clear: the bigger the job, the longer the review path. The median Counter Plan Check TI in 2025 was valued at $50,000, while the median Regular Plan Check TI was valued at $190,000. A clean, complete drawing set is what keeps a mid-size TI eligible for the counter instead of the Regular Plan Check queue.

Restaurants and small businesses can also use the LADBS Restaurant & Small Business Express Program, which assigns a case manager through design, permitting, construction and the Certificate of Occupancy. In October 2026 Mayor Bass signed Executive Directive No. 24, “Streamlining Restaurant Permitting and Strengthening Our Small Businesses.”

What a TI Permit Is Worth

Every LADBS permit carries a declared valuation, which the City uses to calculate fees. It is not the full project cost, since it usually leaves out furniture, equipment and design fees, but it is the best public measure of TI size.

2025 TI permits Declared valuation
25th percentile $38,350
Median $100,000
75th percentile $253,025
Permits valued at $1 million or more 96
Total declared valuation, all 2025 TI permits $530,726,269

The median has stayed at about $100,000 every year since 2020.

What Kinds of Spaces Get Built Out

LADBS records the building use on every permit. Offices dominate, followed by retail and restaurants:

Building use (2025 TI permits) Permits Share
Office 484 38.9%
Retail 196 15.8%
Restaurant 145 11.7%
Medical Office 64 5.1%
Warehouse 36 2.9%
Airport Building 26 2.1%
Restaurant – Take Out 23 1.8%
Bank 22 1.8%

Counting sit-down and take-out together, restaurants accounted for 168 TI permits in 2025. Restaurant build-outs carry an extra step that offices and stores do not: a food facility plan check with the LA County Department of Public Health before the building permit (see the steps below).

Where in Los Angeles TI Work Happens

Planning area (2025) TI permits Share
Central 397 31.9%
West Los Angeles 340 27.3%
South Valley 220 17.7%
North Valley 106 8.5%
South Los Angeles 70 5.6%
East Los Angeles 66 5.3%
Harbor 45 3.6%
Top ZIP codes (2025) Area TI permits
90067 Century City 111
90071 Downtown Financial District 53
90045 Westchester / LAX 45
90048 Beverly Grove 42
90064 West Los Angeles 39
90025 West Los Angeles / Sawtelle 38
90036 Fairfax / Miracle Mile 34
91367 Woodland Hills / Warner Center 33

Century City (90067) alone had 111 TI permits in 2025, more than Downtown’s Financial District (90071) with 53. Office towers turn over suites constantly, and every new tenant means a new build-out.

The Codes That Drive TI Scope and Budget

Accessibility: the path of travel and the 20% rule

When you alter a commercial space, the California Building Code (Chapter 11B, Section 11B-202.4) also requires accessible upgrades to the “path of travel” serving the altered area: the primary entrance, the route to the altered area, the restrooms, drinking fountains and public telephones serving the area, and signs.

How much you must spend depends on a valuation threshold published every year by the Division of the State Architect. For 2026 the threshold is $209,208 ($203,611 in 2025). If your adjusted construction cost is at or below the threshold, path of travel spending is capped at 20% of that cost, spent in a set priority order: entrance first, then the route, then restrooms, telephones and drinking fountains, then parking, signs, storage and alarms. Above the threshold, the full path of travel must comply unless the City finds an unreasonable hardship, and even then you must spend at least 20%.

The adjusted construction cost leaves out architectural and engineering fees, project management, testing and inspection fees, and utility connection fees.

Energy: the 2025 California Energy Code

Permit applications submitted on or after January 1, 2026 must comply with the 2025 Energy Code (Title 24, Part 6), which covers alterations to existing buildings. Lighting and HVAC changes in a TI have to meet it. The California Energy Commission notes that for alterations, the 2025 code replaces certain end-of-life rooftop HVAC units on stores and offices with high-efficiency systems, including heat pumps.

Fire and life safety

The Los Angeles Fire Department’s Fire Life Safety Plan Review covers remodeling and change of use projects, including fire alarm and two-way radio systems. LADBS requires a fire sprinkler permit to install or modify a sprinkler system, with an exception for relocating sprinklers in previously occupied tenant spaces. One licensing detail matters here: a Class B general contractor may not contract for fire sprinkler work unless it holds a C-16 Fire Protection license or subcontracts that work to a C-16 contractor.

Change of use and the Certificate of Occupancy

LADBS states that “a Certificate of Occupancy is not required for a Tenant Improvement project unless the permit is for a Change of Use.” Changing how a space is used requires plan review and a new occupancy approval. A change of use can also raise parking questions. Under AB 2097, the City generally cannot impose minimum parking requirements on most commercial projects within half a mile of a major transit stop. You can check a building’s current approved use with our Certificate of Occupancy lookup.

Food facilities: LA County Public Health comes first

Building, opening or remodeling a restaurant or other food facility, or opening one in a space that never had a County food permit, requires plan check by the LA County Department of Public Health. DPH reviews plans within 20 business days (10 for expedited), and corrected plans within 10. The DPH-approved plans then go to Building and Safety for permits before construction starts, and DPH does a preliminary inspection when the project is about 80% complete.

Step by Step: Permitting a Commercial TI in Los Angeles

  1. Confirm the use and zoning. Check whether your planned use matches the space’s approved use (no change of use) or needs a new one. Our zoning lookup and Certificate of Occupancy lookup show what the City has on record.
  2. Pull the permit history. Earlier unpermitted work in the suite becomes your problem at plan check. Search the address with our permit search.
  3. Survey and design. Field-measure existing conditions, then prepare architectural, MEP, Title 24 energy and accessibility (path of travel) drawings.
  4. Food use? File with Public Health first. Restaurants and other food facilities need DPH-approved plans before the building permit.
  5. Submit to LADBS. Applications go through ePlanLA. The project size and scope decide Counter, Expanded Counter or Regular Plan Check.
  6. Clear fire and life safety review. Fire sprinkler and fire alarm plans are reviewed and permitted alongside the building permit.
  7. Answer corrections and pull the permit. Then build, pass rough and final inspections, and close the permit.
  8. Get the Certificate of Occupancy if the use changed. A TI with no change of use finishes when the permit is finaled.

Most TI permits do get finished. Of the TI permits LADBS issued in 2023, 982 (83%) had been finaled or received a Certificate of Occupancy by November 2026, and 11 had expired.

How We Got These Numbers

  • Source: City of Los Angeles open data, “Building and Safety – Building Permits Issued from 2020 to Present” (LADBS), with permits issued through November 21, 2026.
  • What we counted: permits with permit type “Bldg-Alter/Repair” and sub-type “Commercial” (37,091 permits since 2020) whose LADBS work description mentions “tenant improvement”, “T.I.” or “TI” (8,599 permits). Permits that describe TI work in other words are not counted, so the true number is likely higher.
  • Valuation is the declared valuation on the permit, used by LADBS to calculate fees. It is not the total project cost.
  • Years are by permit issue date. 2026 is a partial year.

Frequently Asked Questions

Do I need a permit for a commercial tenant improvement in Los Angeles?

Almost always. LADBS says commercial tenant improvements require plan review for accessibility, fire and life safety. Only 1 of 8,599 TI permits issued since 2020 skipped plan check as an express permit.

How long does a tenant improvement permit take in Los Angeles?

It depends on the plan check path. Counter Plan Check reviews small and medium projects the same day, Expanded Counter Plan Check assigns plans within a few days, and Regular Plan Check returns plans within weeks depending on workload. Restaurants add LA County Public Health plan check, which takes up to 20 business days.

How much does a commercial TI cost in Los Angeles?

It varies with size, use and condition of the space. The median declared valuation on 2025 LADBS tenant improvement permits was $100,000, and half fell between $38,350 and $253,025. Declared valuation is the figure used for permit fees, not the full project cost.

Does a tenant improvement trigger ADA upgrades?

Yes. California Building Code Section 11B-202.4 requires accessible upgrades to the path of travel serving the altered area. For 2026, if the adjusted construction cost is at or below $209,208, path of travel spending is capped at 20% of that cost. Above it, full compliance is required unless an unreasonable hardship is approved.

Do I need a new Certificate of Occupancy after a tenant improvement?

Only if the use changes. LADBS states that a Certificate of Occupancy is not required for a tenant improvement unless the permit is for a change of use, such as retail to restaurant.

Planning a build-out in Los Angeles?

CCS Inc. is a licensed California B general contractor (CSLB #1047699) that designs, permits and builds commercial tenant improvements for offices, retail, restaurants and medical spaces. Tell us about your space.

See Our Commercial TI Services →

Or start with our free tools: Permit Search  •  C of O Lookup  •  Zoning Lookup

Sources

Related Reading

Filed Knowledge Permit
02 Talk to a specialist

Free 15-minute consultation. No pressure, just a clear next step.

A licensed compliance specialist reviews your permit history and answers your questions. We'll tell you if there's a problem - and what to do about it.

Continue Reading

More from the field.

01
KNOWLEDGE NOV 12, 2026

LADBS Code Enforcement Statistics 2026: How Long Violations Stay Open in LA

Read article →
02
KNOWLEDGE NOV 11, 2026

California Contractor License Statistics 2026: What CSLB Data Shows

Read article →
03
KNOWLEDGE JUL 27, 2026

Watch the Recording: California Building Code Mistakes Every Property Owner Should Avoid (AOA + CCS Webinar)

Read article →
Call(323) 405-8909 ScheduleFree 15 min

Get in Touch

or

Message Sent!

Thank you for reaching out. A member of our team will get back to you within 1 business day.