How Long Does It Take to Build an ADU in Los Angeles?

How Long Does It Take to Build an ADU in Los Angeles?

One of the most common questions homeowners ask when planning an ADU is: “How long will this take?” The complete timeline from initial planning to move-in ready typically ranges from 6-18 months in Los Angeles, depending on project complexity, permit processing times, and construction type. This comprehensive guide breaks down every phase of ADU construction so you know exactly what to expect.

Quick Timeline Overview

ADU Type
Fastest Possible
Typical Timeline
Complex Projects
Pre-Approved Plans (New Construction)
5-7 months
7-10 months
10-14 months
Custom Design (New Construction)
8-10 months
10-14 months
14-18 months
Garage Conversion
4-6 months
6-9 months
9-12 months
Attached ADU
5-7 months
7-11 months
11-15 months
JADU (Interior Conversion)
3-5 months
5-7 months
7-10 months
Prefab/Modular ADU
4-6 months
6-9 months
9-12 months

Complete Phase-by-Phase Timeline

Phase 1: Initial Planning & Decision Making

Duration: 2-6 weeks

Task
Time Required
Details
Research & education
1-2 weeks
Learning about ADUs, regulations, options
Budget development
3-5 days
Determining financing, getting estimates
Property assessment
1-2 weeks
Understanding your lot’s potential, constraints
Contractor selection
1-3 weeks
Interviewing, comparing bids, checking references
Contract negotiation
3-7 days
Finalizing scope, pricing, timeline

Pro Tip:Use our ADU Eligibility Check and Cost Calculator to accelerate this phase.

Phase 2: Design & Engineering

Duration: 4-12 weeks

Option A: Pre-Approved Standard Plans

Duration: 4-6 weeks

  • Select from LA’s Standard Plan Program
  • Plans already reviewed and approved by LADBS
  • Minimal customization (mainly site-specific details)
  • Architectural review: 1-2 weeks
  • Site-specific engineering: 2-3 weeks
  • Survey and civil work: 1-2 weeks

Typical cost: $5,000 – $12,000

Option B: Custom Design

Duration: 8-12 weeks

Design Stage
Duration
Deliverables
Initial Consultation
1 week
Program requirements, preliminary concepts
Schematic Design
2-3 weeks
Floor plans, elevations, design direction
Design Development
2-3 weeks
Refined plans, materials selection, 3D renders
Construction Documents
3-4 weeks
Detailed plans for permitting and construction
Structural Engineering
2-3 weeks
Foundation, framing calculations (concurrent)
MEP Engineering
2-3 weeks
Mechanical, electrical, plumbing (concurrent)
Civil/Survey
1-2 weeks
Site plan, grading, utility locations

Typical cost: $12,000 – $30,000

Time-Saving Strategy: Many of these tasks can run concurrently with experienced design teams.

Phase 3: Permit Application & Approval

Duration: 6-16 weeks

Ministerial ADU Approval (Most ADUs)

Target: 60 days per state law, Reality: 8-16 weeks

Step
Timeline
Notes
Plan check submission
1-3 days
Online submission via LADBS
Initial review
2-4 weeks
LADBS first review cycle
Corrections/resubmittal
1-2 weeks
Address review comments
Second review
2-3 weeks
Verify corrections
Additional reviews (if needed)
2-4 weeks
Complex projects may need 3rd review
Permit issuance
3-5 days
After final approval

Common Delays:

  • Incomplete plan sets: +2-4 weeks
  • Hillside/coastal zone properties: +4-8 weeks additional review
  • HPOZ (Historic) districts: +3-6 weeks for design review
  • Easement issues: +2-6 weeks to resolve
  • Unpermitted work discovered: +4-12 weeks to remediate

Note:If you have existing code violations or unpermitted construction, these must be resolved before ADU permits are issued. As code compliance specialists, we can help expedite this process.

Discretionary Review Projects

Duration: 4-9 months (rare for standard ADUs)

Required if your ADU needs:

  • Variance
  • Conditional Use Permit
  • Environmental review
  • Coastal Commission approval

Most standard ADUs avoid discretionary review thanks to state law.

Phase 4: Pre-Construction

Duration: 2-4 weeks

Task
Duration
Details
Finalize material selections
1 week
Finishes, fixtures, appliances, colors
Order long-lead items
Ongoing
Windows, doors, special materials
Schedule subcontractors
1 week
Coordinate trades, timelines
Site preparation planning
3-5 days
Access, staging, protection of existing
Underground utility location
1-2 weeks
Call 811, private locates if needed
Tree protection (if required)
1-3 days
Fencing, protective measures

Phase 5: Construction

Duration: 16-32 weeks

Detailed Construction Timeline (800 sq ft Detached ADU Example)

Construction Phase
Duration
Key Activities
Week 1-2: Site Preparation
1-2 weeks
– Establish access routes
– Set up temporary fencing
– Demolition if needed
– Clear and grade site
– Tree protection
Week 2-3: Rough Grading & Utilities
1-2 weeks
– Excavation for utilities
– Trenching for water, sewer, electric
– Underground conduit installation
– Rough grading
– Compaction testing
Week 3-6: Foundation
3-4 weeks
– Foundation excavation
– Rebar installation
– Plumbing under-slab
– Foundation inspection
– Concrete pour
– Cure time (7+ days)
– Backfill and compact
Week 7-12: Framing
5-6 weeks
– Floor framing (if raised)
– Wall framing
– Roof framing
– Sheathing
– Framing inspection
– Windows and exterior doors
– House wrap/weather barrier
Week 13-14: Roofing
1-2 weeks
– Underlayment
– Roofing material installation
– Flashing
– Gutters
– Roof inspection
Week 13-17: Rough Mechanicals
4-5 weeks
– Rough plumbing
– Rough electrical
– HVAC installation
– Ductwork
– Gas lines (if applicable)
– Rough inspection (critical milestone)
Week 17-19: Insulation & Drywall
2-3 weeks
– Insulation installation
– Insulation inspection
– Drywall hanging
– Taping and mudding
– Sanding
– Texture
Week 19-21: Exterior Finishes
2-3 weeks
– Siding installation
– Exterior paint/stain
– Trim work
– Soffit and fascia
– Exterior lighting
Week 21-26: Interior Finishes
5-6 weeks
– Interior paint
– Flooring installation
– Cabinets
– Countertops
– Trim and doors
– Tile work (bathroom/kitchen)
– Hardware installation
Week 26-28: Finish Mechanicals
2-3 weeks
– Plumbing fixtures
– Electrical fixtures
– HVAC registers/thermostats
– Appliance installation
– Final connections
Week 28-30: Final Details
2-3 weeks
– Touch-up painting
– Hardware adjustments
– Landscaping restoration
– Driveway/walkways
– Final cleaning
– Punch list items
Week 30-32: Inspections & Close-out
2-3 weeks
– Final building inspection
– Final electrical inspection
– Final plumbing inspection
– Final mechanical inspection
– Corrections if needed
– Certificate of Occupancy

Total Construction: 20-32 weeks (5-8 months)

Construction Timeline Variations by ADU Type

Garage Conversion (600 sq ft):

  • Site prep: 1 week (minimal)
  • Foundation: Already exists (repairs only: 1-2 weeks)
  • Framing: 2-3 weeks (interior partitions, openings)
  • Utilities: 2-3 weeks (shorter runs)
  • Finishes: 4-6 weeks
  • Total: 12-20 weeks

Attached ADU (700 sq ft):

  • Site prep: 1 week
  • Foundation: 2-3 weeks (ties into existing)
  • Framing: 4-5 weeks (one wall exists)
  • Roof integration: 1-2 weeks
  • Utilities: 3-4 weeks
  • Finishes: 5-7 weeks
  • Total: 16-24 weeks

Two-Story ADU (1,200 sq ft):

  • Site prep: 2 weeks
  • Foundation: 4 weeks (larger, more complex)
  • Framing: 8-10 weeks (two stories)
  • Utilities: 5-6 weeks (two floors)
  • Finishes: 8-10 weeks (twice the area)
  • Total: 28-40 weeks

Common Delays and How to Avoid Them

Top 10 Timeline Killers

Delay Cause
Typical Impact
Prevention Strategy
Permit plan corrections
+4-8 weeks
Hire experienced designers; submit complete, accurate plans
Unpermitted existing work
+6-16 weeks
Identify and resolve before ADU application
Material delivery delays
+2-6 weeks
Order long-lead items early; have backup options
Weather delays
+1-4 weeks
Plan around rainy season; have weather contingencies
Failed inspections
+1-3 weeks each
Work with experienced contractors; pre-inspect internally
Subcontractor scheduling
+2-6 weeks
Lock in subs early; have backup trades lined up
Design changes mid-project
+2-8 weeks
Finalize all decisions before breaking ground
Utility connection delays
+3-8 weeks
Apply for utility services early; coordinate with DWP
Easement/title issues
+4-12 weeks
Order title report during design phase
Soil/foundation issues
+2-6 weeks
Geotechnical survey for hillside/problem soils

Seasonal Considerations

Season
Pros
Cons
Timeline Impact
Spring (Mar-May)
Good weather, full work days
Contractor availability tight
Standard timeline
Summer (Jun-Aug)
Long days, minimal rain
Very hot, vacation schedules
Standard timeline
Fall (Sep-Nov)
Ideal weather, good availability
Holiday slowdowns late
Standard to +1 week
Winter (Dec-Feb)
Better contractor availability
Rain delays, holidays, short days
+2-4 weeks typical

Best time to start permitting: Fall (Oct-Nov) to get permits by spring

Best time to start construction: Late spring (Apr-May) to finish before winter

Timeline Acceleration Strategies

How to Shorten Your ADU Timeline

  1. Use Pre-Approved Plans
    • Saves 4-6 weeks in design
    • Faster permit approval (as low as 30-60 days)
    • Plans already vetted for code compliance
    • Total time savings: 6-10 weeks
  2. Hire Design-Build Contractor
    • Single point of contact
    • Concurrent design and permitting prep
    • Better coordination = fewer delays
    • Total time savings: 3-6 weeks
  3. Resolve Existing Violations Early
    • Don’t wait for plan check to discover issues
    • Proactively legalize unpermitted work
    • We specialize in code compliance and violation remediation
    • Total time savings: 6-12 weeks
  4. Pre-Order Long-Lead Materials
    • Windows: 6-12 week lead time
    • Custom doors: 8-14 weeks
    • Appliances: 4-8 weeks
    • Order during permitting phase
    • Total time savings: 4-8 weeks
  5. Consider Prefab/Modular
    • Manufactured while permits process
    • Faster on-site installation (2-4 weeks vs 20-30)
    • Weather-independent factory construction
    • Total time savings: 8-16 weeks
  6. Fast-Track Financing
    • Get pre-approved before design
    • Have funding ready when permits issued
    • Avoid construction delays waiting for loan
    • Total time savings: 2-6 weeks
  7. Make All Decisions Early
    • Finalize finishes before permits submitted
    • No mid-construction changes
    • Keeps project on schedule
    • Total time savings: 2-4 weeks
  8. Work with Experienced ADU Specialist
    • Knows LADBS processes and inspectors
    • Anticipates and prevents issues
    • Established trade relationships
    • Total time savings: 4-8 weeks

Combined potential time savings: 3-6 months off total timeline

Realistic Timeline Expectations by Project Complexity

Simple/Fast-Track Project

Total: 5-8 months

Characteristics:

  • Pre-approved plans or simple custom design
  • Flat lot, no easements or unusual constraints
  • No existing violations
  • Standard finishes, readily available materials
  • Garage conversion or small detached ADU
  • Experienced contractor
  • No weather delays

Timeline breakdown:

  • Planning: 2-3 weeks
  • Design: 4-6 weeks
  • Permits: 8-12 weeks
  • Pre-construction: 2 weeks
  • Construction: 12-20 weeks

Typical/Average Project

Total: 10-14 months

Characteristics:

  • Custom design, moderate complexity
  • Standard residential lot
  • Some site challenges (slope, access, utilities)
  • Mid-range finishes
  • Detached or attached ADU, 600-900 sq ft
  • Normal permitting timeline
  • Some minor delays expected

Timeline breakdown:

  • Planning: 3-6 weeks
  • Design: 8-12 weeks
  • Permits: 12-16 weeks
  • Pre-construction: 3 weeks
  • Construction: 20-28 weeks

Complex/Extended Project

Total: 14-20 months

Characteristics:

  • Complex custom design
  • Hillside, coastal zone, or HPOZ property
  • Easement issues or lot constraints
  • Existing violations requiring remediation
  • High-end finishes, custom materials
  • Two-story or large ADU (1,000-1,200 sq ft)
  • Additional agency approvals needed
  • Winter construction period

Timeline breakdown:

  • Planning: 6-8 weeks
  • Design: 12-16 weeks
  • Permits: 16-24 weeks
  • Pre-construction: 4 weeks
  • Construction: 28-40 weeks

Month-by-Month: What to Expect

Typical 12-Month ADU Project Calendar

Month
Phase
What’s Happening
Your Involvement
Month 1
Planning
Research, contractor selection, initial meetings
HIGH – Many decisions to make
Month 2
Design Start
Schematic design, preliminary drawings
HIGH – Design input and approvals
Month 3
Design Completion
Final plans, engineering, material selections
MEDIUM – Finalize finishes and details
Month 4
Permit Submission
Plans submitted to LADBS, initial review
LOW – Waiting for city review
Month 5
Permit Review
Plan check corrections, resubmittals
LOW – Contractor handles corrections
Month 6
Permit Approval
Final permit issued, pre-construction prep
MEDIUM – Final material orders, scheduling
Month 7
Early Construction
Site prep, utilities, foundation
LOW – Progress monitoring
Month 8
Framing
Structure goes up, big visual progress
LOW – Weekly check-ins
Month 9
Rough Mechanicals
Plumbing, electrical, HVAC, roofing
LOW – Occasional site visits
Month 10
Drywall & Exteriors
Insulation, drywall, siding, windows
MEDIUM – Color/finish confirmations
Month 11
Finishes
Paint, flooring, cabinets, fixtures
MEDIUM – Walkthrough, punch list
Month 12
Final & Closeout
Final touches, inspections, Certificate of Occupancy
HIGH – Final inspection, move-in prep

Inspection Timeline & Requirements

Required Inspections During Construction

Inspection Type
When Required
Typical Wait Time
Common Issues
Foundation
Before concrete pour
1-3 days
Rebar spacing, embedments
Under-Slab Plumbing
Before foundation pour
1-2 days
Pressure test, proper slope
Framing
After framing complete
1-3 days
Structural connections, blocking
Rough Plumbing
After rough-in, before insulation
1-3 days
Proper venting, water test
Rough Electrical
After rough-in, before insulation
1-3 days
Box fill, wire sizing, grounding
Rough Mechanical
After HVAC install, before insulation
1-3 days
Duct sizing, proper installation
Insulation
After insulation, before drywall
1-2 days
R-value, coverage, air sealing
Final Building
After completion
3-7 days
Code compliance, safety features
Final Plumbing
After fixtures installed
1-3 days
Fixture installation, water test
Final Electrical
After all electric complete
1-3 days
GFCI/AFCI, panel labeling
Final Mechanical
After HVAC complete
1-3 days
Proper operation, Title 24

Total inspection time built into schedule: 2-4 weeks

After Construction: Move-In Timeline

Duration: 1-3 weeks after final inspection

  • Final cleaning: 1-2 days
  • Utility activation: 3-5 days
  • Landscaping completion: 1-2 weeks
  • Furnishing (if applicable): 1-2 weeks
  • For rentals: Marketing and tenant screening: 2-6 weeks

Project Management: Staying On Schedule

Critical Success Factors

  • Experienced Contractor– Single biggest factor in on-time completion
  • Clear Communication– Weekly updates, immediate issue resolution
  • Buffer Timeline– Add 15-20% contingency to estimates
  • Decision Readiness– Make choices quickly when needed
  • Inspection Coordination– Don’t let inspections create delays
  • Weather Planning– Have rain delay contingencies
  • Material Management– Order early, have backups ready
  • Trade Coordination– Keep subcontractors on schedule

Get Started with Realistic Timelines

Understanding the ADU timeline helps you plan accordingly – whether you’re timing a rental income start, coordinating with family moves, or budgeting for temporary housing during construction.

As experienced Los Angeles ADU contractors, we help you navigate every phase:

  • Accurate timeline projections for your specific project
  • Streamlined permitting and code compliance
  • Resolution of existing violations before starting
  • Proactive project management to prevent delays
  • From initial concept to Certificate of Occupancy

Start your ADU journey with our ADU Eligibility Check and Cost Calculator to understand your project timeline and budget.

Bottom line: Plan for 10-14 months for a typical ADU project, hope for 8-10 months with good luck and planning, and be prepared for 14-18 months if complications arise.