How Long Does It Take to Build an ADU in Los Angeles?
One of the most common questions homeowners ask when planning an ADU is: “How long will this take?” The complete timeline from initial planning to move-in ready typically ranges from 6-18 months in Los Angeles, depending on project complexity, permit processing times, and construction type. This comprehensive guide breaks down every phase of ADU construction so you know exactly what to expect.
Quick Timeline Overview
|
ADU Type
|
Fastest Possible
|
Typical Timeline
|
Complex Projects
|
|---|---|---|---|
|
Pre-Approved Plans (New Construction)
|
5-7 months
|
7-10 months
|
10-14 months
|
|
Custom Design (New Construction)
|
8-10 months
|
10-14 months
|
14-18 months
|
|
Garage Conversion
|
4-6 months
|
6-9 months
|
9-12 months
|
|
Attached ADU
|
5-7 months
|
7-11 months
|
11-15 months
|
|
JADU (Interior Conversion)
|
3-5 months
|
5-7 months
|
7-10 months
|
|
Prefab/Modular ADU
|
4-6 months
|
6-9 months
|
9-12 months
|
Complete Phase-by-Phase Timeline
Phase 1: Initial Planning & Decision Making
Duration: 2-6 weeks
|
Task
|
Time Required
|
Details
|
|---|---|---|
|
Research & education
|
1-2 weeks
|
Learning about ADUs, regulations, options
|
|
Budget development
|
3-5 days
|
Determining financing, getting estimates
|
|
Property assessment
|
1-2 weeks
|
Understanding your lot’s potential, constraints
|
|
Contractor selection
|
1-3 weeks
|
Interviewing, comparing bids, checking references
|
|
Contract negotiation
|
3-7 days
|
Finalizing scope, pricing, timeline
|
Pro Tip:Use our ADU Eligibility Check and Cost Calculator to accelerate this phase.
Phase 2: Design & Engineering
Duration: 4-12 weeks
Option A: Pre-Approved Standard Plans
Duration: 4-6 weeks
- Select from LA’s Standard Plan Program
- Plans already reviewed and approved by LADBS
- Minimal customization (mainly site-specific details)
- Architectural review: 1-2 weeks
- Site-specific engineering: 2-3 weeks
- Survey and civil work: 1-2 weeks
Typical cost: $5,000 – $12,000
Option B: Custom Design
Duration: 8-12 weeks
|
Design Stage
|
Duration
|
Deliverables
|
|---|---|---|
|
Initial Consultation
|
1 week
|
Program requirements, preliminary concepts
|
|
Schematic Design
|
2-3 weeks
|
Floor plans, elevations, design direction
|
|
Design Development
|
2-3 weeks
|
Refined plans, materials selection, 3D renders
|
|
Construction Documents
|
3-4 weeks
|
Detailed plans for permitting and construction
|
|
Structural Engineering
|
2-3 weeks
|
Foundation, framing calculations (concurrent)
|
|
MEP Engineering
|
2-3 weeks
|
Mechanical, electrical, plumbing (concurrent)
|
|
Civil/Survey
|
1-2 weeks
|
Site plan, grading, utility locations
|
Typical cost: $12,000 – $30,000
Time-Saving Strategy: Many of these tasks can run concurrently with experienced design teams.
Phase 3: Permit Application & Approval
Duration: 6-16 weeks
Ministerial ADU Approval (Most ADUs)
Target: 60 days per state law, Reality: 8-16 weeks
|
Step
|
Timeline
|
Notes
|
|---|---|---|
|
Plan check submission
|
1-3 days
|
Online submission via LADBS
|
|
Initial review
|
2-4 weeks
|
LADBS first review cycle
|
|
Corrections/resubmittal
|
1-2 weeks
|
Address review comments
|
|
Second review
|
2-3 weeks
|
Verify corrections
|
|
Additional reviews (if needed)
|
2-4 weeks
|
Complex projects may need 3rd review
|
|
Permit issuance
|
3-5 days
|
After final approval
|
Common Delays:
- Incomplete plan sets: +2-4 weeks
- Hillside/coastal zone properties: +4-8 weeks additional review
- HPOZ (Historic) districts: +3-6 weeks for design review
- Easement issues: +2-6 weeks to resolve
- Unpermitted work discovered: +4-12 weeks to remediate
Note:If you have existing code violations or unpermitted construction, these must be resolved before ADU permits are issued. As code compliance specialists, we can help expedite this process.
Discretionary Review Projects
Duration: 4-9 months (rare for standard ADUs)
Required if your ADU needs:
- Variance
- Conditional Use Permit
- Environmental review
- Coastal Commission approval
Most standard ADUs avoid discretionary review thanks to state law.
Phase 4: Pre-Construction
Duration: 2-4 weeks
|
Task
|
Duration
|
Details
|
|---|---|---|
|
Finalize material selections
|
1 week
|
Finishes, fixtures, appliances, colors
|
|
Order long-lead items
|
Ongoing
|
Windows, doors, special materials
|
|
Schedule subcontractors
|
1 week
|
Coordinate trades, timelines
|
|
Site preparation planning
|
3-5 days
|
Access, staging, protection of existing
|
|
Underground utility location
|
1-2 weeks
|
Call 811, private locates if needed
|
|
Tree protection (if required)
|
1-3 days
|
Fencing, protective measures
|
Phase 5: Construction
Duration: 16-32 weeks
Detailed Construction Timeline (800 sq ft Detached ADU Example)
|
Construction Phase
|
Duration
|
Key Activities
|
|---|---|---|
|
Week 1-2: Site Preparation
|
1-2 weeks
|
– Establish access routes
– Set up temporary fencing – Demolition if needed – Clear and grade site – Tree protection |
|
Week 2-3: Rough Grading & Utilities
|
1-2 weeks
|
– Excavation for utilities
– Trenching for water, sewer, electric – Underground conduit installation – Rough grading – Compaction testing |
|
Week 3-6: Foundation
|
3-4 weeks
|
– Foundation excavation
– Rebar installation – Plumbing under-slab – Foundation inspection – Concrete pour – Cure time (7+ days) – Backfill and compact |
|
Week 7-12: Framing
|
5-6 weeks
|
– Floor framing (if raised)
– Wall framing – Roof framing – Sheathing – Framing inspection – Windows and exterior doors – House wrap/weather barrier |
|
Week 13-14: Roofing
|
1-2 weeks
|
– Underlayment
– Roofing material installation – Flashing – Gutters – Roof inspection |
|
Week 13-17: Rough Mechanicals
|
4-5 weeks
|
– Rough plumbing
– Rough electrical – HVAC installation – Ductwork – Gas lines (if applicable) – Rough inspection (critical milestone) |
|
Week 17-19: Insulation & Drywall
|
2-3 weeks
|
– Insulation installation
– Insulation inspection – Drywall hanging – Taping and mudding – Sanding – Texture |
|
Week 19-21: Exterior Finishes
|
2-3 weeks
|
– Siding installation
– Exterior paint/stain – Trim work – Soffit and fascia – Exterior lighting |
|
Week 21-26: Interior Finishes
|
5-6 weeks
|
– Interior paint
– Flooring installation – Cabinets – Countertops – Trim and doors – Tile work (bathroom/kitchen) – Hardware installation |
|
Week 26-28: Finish Mechanicals
|
2-3 weeks
|
– Plumbing fixtures
– Electrical fixtures – HVAC registers/thermostats – Appliance installation – Final connections |
|
Week 28-30: Final Details
|
2-3 weeks
|
– Touch-up painting
– Hardware adjustments – Landscaping restoration – Driveway/walkways – Final cleaning – Punch list items |
|
Week 30-32: Inspections & Close-out
|
2-3 weeks
|
– Final building inspection
– Final electrical inspection – Final plumbing inspection – Final mechanical inspection – Corrections if needed – Certificate of Occupancy |
Total Construction: 20-32 weeks (5-8 months)
Construction Timeline Variations by ADU Type
Garage Conversion (600 sq ft):
- Site prep: 1 week (minimal)
- Foundation: Already exists (repairs only: 1-2 weeks)
- Framing: 2-3 weeks (interior partitions, openings)
- Utilities: 2-3 weeks (shorter runs)
- Finishes: 4-6 weeks
- Total: 12-20 weeks
Attached ADU (700 sq ft):
- Site prep: 1 week
- Foundation: 2-3 weeks (ties into existing)
- Framing: 4-5 weeks (one wall exists)
- Roof integration: 1-2 weeks
- Utilities: 3-4 weeks
- Finishes: 5-7 weeks
- Total: 16-24 weeks
Two-Story ADU (1,200 sq ft):
- Site prep: 2 weeks
- Foundation: 4 weeks (larger, more complex)
- Framing: 8-10 weeks (two stories)
- Utilities: 5-6 weeks (two floors)
- Finishes: 8-10 weeks (twice the area)
- Total: 28-40 weeks
Common Delays and How to Avoid Them
Top 10 Timeline Killers
|
Delay Cause
|
Typical Impact
|
Prevention Strategy
|
|---|---|---|
|
Permit plan corrections
|
+4-8 weeks
|
Hire experienced designers; submit complete, accurate plans
|
|
Unpermitted existing work
|
+6-16 weeks
|
Identify and resolve before ADU application
|
|
Material delivery delays
|
+2-6 weeks
|
Order long-lead items early; have backup options
|
|
Weather delays
|
+1-4 weeks
|
Plan around rainy season; have weather contingencies
|
|
Failed inspections
|
+1-3 weeks each
|
Work with experienced contractors; pre-inspect internally
|
|
Subcontractor scheduling
|
+2-6 weeks
|
Lock in subs early; have backup trades lined up
|
|
Design changes mid-project
|
+2-8 weeks
|
Finalize all decisions before breaking ground
|
|
Utility connection delays
|
+3-8 weeks
|
Apply for utility services early; coordinate with DWP
|
|
Easement/title issues
|
+4-12 weeks
|
Order title report during design phase
|
|
Soil/foundation issues
|
+2-6 weeks
|
Geotechnical survey for hillside/problem soils
|
Seasonal Considerations
|
Season
|
Pros
|
Cons
|
Timeline Impact
|
|---|---|---|---|
|
Spring (Mar-May)
|
Good weather, full work days
|
Contractor availability tight
|
Standard timeline
|
|
Summer (Jun-Aug)
|
Long days, minimal rain
|
Very hot, vacation schedules
|
Standard timeline
|
|
Fall (Sep-Nov)
|
Ideal weather, good availability
|
Holiday slowdowns late
|
Standard to +1 week
|
|
Winter (Dec-Feb)
|
Better contractor availability
|
Rain delays, holidays, short days
|
+2-4 weeks typical
|
Best time to start permitting: Fall (Oct-Nov) to get permits by spring
Best time to start construction: Late spring (Apr-May) to finish before winter
Timeline Acceleration Strategies
How to Shorten Your ADU Timeline
- Use Pre-Approved Plans
- Saves 4-6 weeks in design
- Faster permit approval (as low as 30-60 days)
- Plans already vetted for code compliance
- Total time savings: 6-10 weeks
- Hire Design-Build Contractor
- Single point of contact
- Concurrent design and permitting prep
- Better coordination = fewer delays
- Total time savings: 3-6 weeks
- Resolve Existing Violations Early
- Don’t wait for plan check to discover issues
- Proactively legalize unpermitted work
- We specialize in code compliance and violation remediation
- Total time savings: 6-12 weeks
- Pre-Order Long-Lead Materials
- Windows: 6-12 week lead time
- Custom doors: 8-14 weeks
- Appliances: 4-8 weeks
- Order during permitting phase
- Total time savings: 4-8 weeks
- Consider Prefab/Modular
- Manufactured while permits process
- Faster on-site installation (2-4 weeks vs 20-30)
- Weather-independent factory construction
- Total time savings: 8-16 weeks
- Fast-Track Financing
- Get pre-approved before design
- Have funding ready when permits issued
- Avoid construction delays waiting for loan
- Total time savings: 2-6 weeks
- Make All Decisions Early
- Finalize finishes before permits submitted
- No mid-construction changes
- Keeps project on schedule
- Total time savings: 2-4 weeks
- Work with Experienced ADU Specialist
- Knows LADBS processes and inspectors
- Anticipates and prevents issues
- Established trade relationships
- Total time savings: 4-8 weeks
Combined potential time savings: 3-6 months off total timeline
Realistic Timeline Expectations by Project Complexity
Simple/Fast-Track Project
Total: 5-8 months
Characteristics:
- Pre-approved plans or simple custom design
- Flat lot, no easements or unusual constraints
- No existing violations
- Standard finishes, readily available materials
- Garage conversion or small detached ADU
- Experienced contractor
- No weather delays
Timeline breakdown:
- Planning: 2-3 weeks
- Design: 4-6 weeks
- Permits: 8-12 weeks
- Pre-construction: 2 weeks
- Construction: 12-20 weeks
Typical/Average Project
Total: 10-14 months
Characteristics:
- Custom design, moderate complexity
- Standard residential lot
- Some site challenges (slope, access, utilities)
- Mid-range finishes
- Detached or attached ADU, 600-900 sq ft
- Normal permitting timeline
- Some minor delays expected
Timeline breakdown:
- Planning: 3-6 weeks
- Design: 8-12 weeks
- Permits: 12-16 weeks
- Pre-construction: 3 weeks
- Construction: 20-28 weeks
Complex/Extended Project
Total: 14-20 months
Characteristics:
- Complex custom design
- Hillside, coastal zone, or HPOZ property
- Easement issues or lot constraints
- Existing violations requiring remediation
- High-end finishes, custom materials
- Two-story or large ADU (1,000-1,200 sq ft)
- Additional agency approvals needed
- Winter construction period
Timeline breakdown:
- Planning: 6-8 weeks
- Design: 12-16 weeks
- Permits: 16-24 weeks
- Pre-construction: 4 weeks
- Construction: 28-40 weeks
Month-by-Month: What to Expect
Typical 12-Month ADU Project Calendar
|
Month
|
Phase
|
What’s Happening
|
Your Involvement
|
|---|---|---|---|
|
Month 1
|
Planning
|
Research, contractor selection, initial meetings
|
HIGH – Many decisions to make
|
|
Month 2
|
Design Start
|
Schematic design, preliminary drawings
|
HIGH – Design input and approvals
|
|
Month 3
|
Design Completion
|
Final plans, engineering, material selections
|
MEDIUM – Finalize finishes and details
|
|
Month 4
|
Permit Submission
|
Plans submitted to LADBS, initial review
|
LOW – Waiting for city review
|
|
Month 5
|
Permit Review
|
Plan check corrections, resubmittals
|
LOW – Contractor handles corrections
|
|
Month 6
|
Permit Approval
|
Final permit issued, pre-construction prep
|
MEDIUM – Final material orders, scheduling
|
|
Month 7
|
Early Construction
|
Site prep, utilities, foundation
|
LOW – Progress monitoring
|
|
Month 8
|
Framing
|
Structure goes up, big visual progress
|
LOW – Weekly check-ins
|
|
Month 9
|
Rough Mechanicals
|
Plumbing, electrical, HVAC, roofing
|
LOW – Occasional site visits
|
|
Month 10
|
Drywall & Exteriors
|
Insulation, drywall, siding, windows
|
MEDIUM – Color/finish confirmations
|
|
Month 11
|
Finishes
|
Paint, flooring, cabinets, fixtures
|
MEDIUM – Walkthrough, punch list
|
|
Month 12
|
Final & Closeout
|
Final touches, inspections, Certificate of Occupancy
|
HIGH – Final inspection, move-in prep
|
Inspection Timeline & Requirements
Required Inspections During Construction
|
Inspection Type
|
When Required
|
Typical Wait Time
|
Common Issues
|
|---|---|---|---|
|
Foundation
|
Before concrete pour
|
1-3 days
|
Rebar spacing, embedments
|
|
Under-Slab Plumbing
|
Before foundation pour
|
1-2 days
|
Pressure test, proper slope
|
|
Framing
|
After framing complete
|
1-3 days
|
Structural connections, blocking
|
|
Rough Plumbing
|
After rough-in, before insulation
|
1-3 days
|
Proper venting, water test
|
|
Rough Electrical
|
After rough-in, before insulation
|
1-3 days
|
Box fill, wire sizing, grounding
|
|
Rough Mechanical
|
After HVAC install, before insulation
|
1-3 days
|
Duct sizing, proper installation
|
|
Insulation
|
After insulation, before drywall
|
1-2 days
|
R-value, coverage, air sealing
|
|
Final Building
|
After completion
|
3-7 days
|
Code compliance, safety features
|
|
Final Plumbing
|
After fixtures installed
|
1-3 days
|
Fixture installation, water test
|
|
Final Electrical
|
After all electric complete
|
1-3 days
|
GFCI/AFCI, panel labeling
|
|
Final Mechanical
|
After HVAC complete
|
1-3 days
|
Proper operation, Title 24
|
Total inspection time built into schedule: 2-4 weeks
After Construction: Move-In Timeline
Duration: 1-3 weeks after final inspection
- Final cleaning: 1-2 days
- Utility activation: 3-5 days
- Landscaping completion: 1-2 weeks
- Furnishing (if applicable): 1-2 weeks
- For rentals: Marketing and tenant screening: 2-6 weeks
Project Management: Staying On Schedule
Critical Success Factors
- Experienced Contractor– Single biggest factor in on-time completion
- Clear Communication– Weekly updates, immediate issue resolution
- Buffer Timeline– Add 15-20% contingency to estimates
- Decision Readiness– Make choices quickly when needed
- Inspection Coordination– Don’t let inspections create delays
- Weather Planning– Have rain delay contingencies
- Material Management– Order early, have backups ready
- Trade Coordination– Keep subcontractors on schedule
Get Started with Realistic Timelines
Understanding the ADU timeline helps you plan accordingly – whether you’re timing a rental income start, coordinating with family moves, or budgeting for temporary housing during construction.
As experienced Los Angeles ADU contractors, we help you navigate every phase:
- Accurate timeline projections for your specific project
- Streamlined permitting and code compliance
- Resolution of existing violations before starting
- Proactive project management to prevent delays
- From initial concept to Certificate of Occupancy
Start your ADU journey with our ADU Eligibility Check and Cost Calculator to understand your project timeline and budget.
Bottom line: Plan for 10-14 months for a typical ADU project, hope for 8-10 months with good luck and planning, and be prepared for 14-18 months if complications arise.



